Here are the times reported by students for assignment one. Students were to estimate the time they thought the assignment would take and record the time they actually spent. Time on the project is divided into five areas: requirement analysis, design, coding, debugging and testing.
Req. Analysis | Design | Coding | Debugging | Testing | Total | |
Estimate | 1.2 | 3.9 | 14.6 | 4.6 | 2.6 | 26.1 |
Actual | 2.5 | 5.3 | 21.5 | 6.3 | 2.8 | 37.3 |
Req. Analysis | Design | Coding | Debugging | Testing | Total |
10 | 10 | 10 | 30.0 | ||
1 | 4 | 8 | 3 | 4 | 20.0 |
1 | 5 | 10 | 10 | 1 | 27.0 |
1 | 3 | 5 | 2 | 2 | 13.0 |
3 | 2 | 5 | 16 | 4 | 30.0 |
0.5 | 6 | 12 | 2 | 2 | 22.5 |
2 | 2 | 8 | 4 | 3 | 19.0 |
1 | 2 | 16 | 4 | 2 | 25.0 |
0.5 | 1 | 20 | 1 | 0.5 | 23.0 |
1 | 5 | 30 | 5 | 5 | 46.0 |
3 | 8 | 3 | 1.5 | 15.5 | |
1 | 2 | 4 | 2 | 1 | 10.0 |
1 | 1.5 | 20 | 2 | 24.5 | |
1 | 5 | 10 | 1 | 17.0 | |
2 | 2 | 12 | 2 | 1 | 19.0 |
2 | 10 | 70 | 13 | 5 | 100.0 |
1 | 6 | 4 | 3 | 1 | 15.0 |
0.5 | 1 | 10 | 1 | 1 | 13.5 |
Req. Analysis | Design | Coding | Debugging | Testing | Total |
5 | 16 | 5 | 26.0 | ||
4 | 4 | 20 | 0.5 | 0.5 | 29.0 |
2 | 4 | 17 | 18 | 1 | 42.0 |
3 | 5 | 25 | 5 | 1 | 39.0 |
5 | 10 | 2 | 5 | 5 | 27.0 |
2 | 4 | 20 | 4 | 4 | 34.0 |
6 | 4 | 8 | 21 | 6 | 45.0 |
1 | 13 | 16 | 5 | 3 | 38.0 |
6 | 4 | 15 | 6 | 3 | 34.0 |
1.5 | 3 | 18 | 2 | 2 | 26.5 |
1 | 2 | 15 | 1 | 0.5 | 19.5 |
1 | 2 | 25 | 3 | 2 | 33.0 |
5 | 20 | 6 | 3 | 34.0 | |
1 | 3 | 8 | 3 | 2 | 17.0 |
2 | 3 | 30 | 4 | 39.0 | |
1 | 11 | 10 | 1 | 23.0 | |
2 | 3 | 16 | 6 | 1 | 28.0 |
3 | 10 | 100 | 12 | 6 | 131.0 |
3 | 7 | 8 | 9 | 5 | 32.0 |
1 | 3 | 40 | 3 | 2 | 49.0 |